The underground plumbing and electrial rough-in continues on the east side of Phase 1. The formwork for the oval classroom has been built and the oval walls have been poured. This area will be split into two semi-circular instructional classrooms, each with a capacity of 120 students. The footings for the 350 seat lecture hall have begun and the metal decking continues in Phase 1. The basement walls are nearing completion.