conceptual drawing of LSRCA conceptual drawing shows the social hub in the Lancer Sport and Recreation Centre.

UWSA issues update on sport centre progress

Design work on the $73 million Lancer Sport and Recreation Centre (LSRC) is continuing through the summer, with early interior work on the current St. Denis Centre expected to start by late summer, according Jeremiah Bowers, president of the University of Windsor Students’ Alliance.

He says sewer work on the project is currently out for tender with a tentative start date of later this summer, and the main portion of the project is scheduled to go to tender in early 2019 with ground-breaking expected by summer 2019.

The LSRC will offer a modern space to foster athletic excellence and support high-quality recreational services for thousands of students and members of the community. For more information on the project, visit https://www.uwindsor.ca/campustransformation/345/lsrc-overview.