Implementation timeline

  • Spring 2022
    • Brightspace selected
  • August 2022
    • Contract completed, public announcement
    • Vendor kick-off
    • Implementation and training planning
    • Training of administrators
    • Early adopters/pilot instructors training
  • September 2022
    • Small Fall pilot begins
    • Training preparation
    • Technical integrations begin
  • October 2022
    • Sandbox sites available
    • Training begins
    • Migration begins
  • November 2022
    • Winter course sites available
  • January 2023
    • All courses taught using Brightspace
    • Deployment completed
  • March 2023
    • Summer course sites available
  • April 28, 2023
    • Blackboard contract ends
    • Brightspace implementation complete